WindPermit validConstanța

Wind 7.5 MW · Constanța

Installed capacity

7.5MW

Stage

Permit valid

Substation

hidden value

Technical data

Technology
Wind
Installed capacity
7.5 MW
Approved capacity
7.5 MW
County
Constanța
Connection point
hidden value
Connection voltage
110 kV
Permit no.
hidden value
Permit issued
10 February 2026
Connection contract
Not signed
Contract number
hidden value
Estimated commissioning
31 December 2026
Connection certificate
hidden value
Generation licence
hidden value

With the page unlocked

  • which substation it connects to, and who else is queuing there
  • who holds the project: the company, its tax ID and its other projects
  • estimated generation and revenue, at actual market prices
  • comparable projects in the county, and what changed in the registers
Sign in for details

Estimated generation and revenue

Specific yield
hidden value
Estimated generation
hidden value
Average captured price
hidden value
Estimated annual revenue
hidden value

Competition at the connection substation

Competition level
hidden value
Other projects at the same substation
hidden value
Total capacity requested
hidden value
Planned grid reinforcement works
hidden value

Solar and wind resource at the site

Specific solar yield
hidden value
Optimal panel tilt
hidden value
Mean wind speed at 100 m
hidden value
Mean wind speed at 150 m
hidden value
Mean temperature
hidden value

Contract for difference (CfD)

Contract for Difference (CfD)
hidden value
Strike price
hidden value
Committed commissioning date
hidden value

Permit holder

Name
hidden value
Tax ID (CUI)
hidden value
Other projects
hidden value

Similar projects in the county

Wind projects in Constanța
hidden value
Capacity range
hidden value

History in the operator's register

Changes
hidden value

Data sources Connection register of Rețele Electrice România (formerly E-Distribuție) Resource Global Solar Atlas and Global Wind Atlas, long-term averages, approx. 5 km resolution Public ID RO-P125411 Checked 7 October 2026