Energy projects in Buzău
In Buzău County, 37 projects above 1 MW are requesting grid connection, 1,993 MW in total. 23 have a signed connection contract.
There are 24 solar PV parks (269 MW), 3 wind farms (720 MW), 1 battery storage facility (99 MW) and 1 hybrid project (8 MW). The largest is 441.0 MW, and 8 projects exceed 50 MW. 7 projects hold a valid grid permit, and 7 have an expired permit.