In Mehedinți County, 31 projects above 1 MW are requesting grid connection, 1,406 MW in total. 19 have a signed connection contract.

There are 14 solar PV parks (435 MW), 11 hybrid projects (185 MW), 3 battery storage facilities (82 MW), 1 hydropower plant (392 MW) and 1 wind farm (74 MW). The largest is 392.0 MW, and 6 projects exceed 50 MW. 5 projects hold a valid grid permit, and 7 have an expired permit.