Energy projects in Argeș

In Argeș County, 50 projects above 1 MW are requesting grid connection, 2,325 MW in total. 23 have a signed connection contract.

There are 26 solar PV parks (1,081 MW), 17 hybrid projects (196 MW) and 6 battery storage facilities (654 MW). The largest is 393.9 MW, and 9 projects exceed 50 MW. 12 projects hold a valid grid permit, and 15 have an expired permit.

ProjectStage
393.9 MW energy projectPermit expired
344.6 MW solar PV parkPermit valid
302.9 MW solar PV park · BuzoeștiConnection contract
299.0 MW battery storage facilityPermit valid
199.7 MW battery storage facilityConnection contract
143.2 MW battery storage facilityPermit expired
107.5 MW solar PV parkConnection contract
60.0 MW solar PV park · Bughea de SusConnection contract
59.8 MW hybrid project · SuseniPermit valid
49.3 MW hybrid projectConnection contract
40.2 MW solar PV park · MioareleConnection contract
38.5 MW solar PV parkConnection contract
37.1 MW solar PV park · CăteascaPermit expired
35.0 MW solar PV park · RăteștiPermit expired
30.0 MW hybrid project · ViișoaraPermit valid
24.9 MW solar PV park · Bughea de JosConnection contract
20.8 MW solar PV parkConnection contract
17.8 MW solar PV parkConnection contract
14.2 MW solar PV park · SuseniConnection contract
13.2 MW hybrid project · BraduConnection contract
6.8 MW battery storage facilityConnection contract
6.7 MW hybrid project · Curtea de ArgeșPermit valid
6.7 MW hybrid project · Curtea de ArgeșPermit valid
5.8 MW hybrid project · DomneștiConnection contract
5.0 MW hybrid project · CăteascaConnection contract
4.9 MW solar PV park · CăteascaConnection contract
4.0 MW solar PV park · BraduConnection contract
3.3 MW solar PV park · RăteștiPermit expired
3.2 MW hybrid projectConnection contract
3.2 MW solar PV park · AlbotaConnection contract
3.1 MW hybrid project · ȘtefăneștiPermit valid
3.1 MW solar PV parkPermit valid
3.0 MW solar PV park · TopoloveniPermit expired
3.0 MW solar PV park · DărmăneștiConnection contract
3.0 MW hybrid project · HârtieștiPermit valid
2.7 MW hybrid project · CosteștiConnection contract
2.7 MW solar PV park · ȘtefăneștiPermit expired
2.7 MW solar PV park · RăteștiPermit expired
2.6 MW battery storage facilityPermit expired
2.4 MW solar PV park · DavideștiPermit expired
2.4 MW hybrid project · DavideștiPermit valid
2.2 MW battery storage facility · PriboieniPermit expired
1.8 MW solar PV park · Lunca CorbuluiPermit expired
1.5 MW solar PV parkPermit expired
1.5 MW hybrid projectPermit valid
1.4 MW hybrid project · ȘtefăneștiPermit valid
1.2 MW solar PV park · CăteascaPermit expired
1.1 MW solar PV park · ȘtefăneștiPermit expired
1.1 MW hybrid project · VedeaConnection contract
1.0 MW hybrid project · LeordeniConnection contract

Other counties