Energy projects in Bihor

In Bihor County, 67 projects above 1 MW are requesting grid connection, 3,229 MW in total. 51 have a signed connection contract.

There are 59 solar PV parks (1,634 MW), 4 hybrid projects (1,064 MW), 3 battery storage facilities (520 MW) and 1 wind farm (12 MW). The largest is 586.8 MW, and 12 projects exceed 50 MW. 14 projects hold a valid grid permit, and 2 have an expired permit.

ProjectStage
586.8 MW solar PV parkConnection contract
382.2 MW hybrid projectConnection contract
364.1 MW hybrid projectConnection contract
293.8 MW battery storage facilityConnection contract
178.5 MW battery storage facilityPermit valid
167.4 MW hybrid projectPermit valid
149.8 MW hybrid project · OradeaConnection contract
89.1 MW solar PV park · ȚețcheaConnection contract
77.5 MW solar PV park · CefaConnection contract
70.4 MW solar PV parkPermit valid
61.8 MW solar PV park · SăcădatConnection contract
59.1 MW solar PV parkConnection contract
49.0 MW solar PV park · AlpareaConnection contract
49.0 MW solar PV park · SântandreiConnection contract
49.0 MW solar PV park · SântandreiConnection contract
48.2 MW battery storage facilityConnection contract
48.1 MW solar PV park · OșorheiConnection contract
45.2 MW solar PV park · BeiușConnection contract
45.2 MW solar PV park · BeiușConnection contract
42.9 MW solar PV park · AștileuConnection contract
41.4 MW solar PV park · Avram IancuConnection contract
40.0 MW solar PV park · DiosigPermit valid
35.0 MW solar PV park · AștileuConnection contract
32.0 MW solar PV park · Avram IancuConnection contract
29.4 MW solar PV park · ChișlazConnection contract
28.5 MW solar PV park · Avram IancuConnection contract
21.7 MW solar PV park · Avram IancuPermit valid
11.5 MW wind farm · NucetConnection contract
9.0 MW solar PV park · AbrămuțConnection contract
8.2 MW solar PV parkConnection contract
7.7 MW solar PV park · Avram IancuPermit valid
5.0 MW solar PV parkConnection contract
5.0 MW solar PV parkConnection contract
5.0 MW solar PV park · Lazuri de BeiușPermit valid
4.5 MW solar PV parkConnection contract
4.1 MW solar PV park · LuncaPermit valid
4.1 MW solar PV parkConnection contract
4.0 MW solar PV park · BorșConnection contract
4.0 MW solar PV parkConnection contract
4.0 MW solar PV park · BihariaConnection contract
4.0 MW solar PV parkPermit valid
4.0 MW solar PV park · GepiuConnection contract
4.0 MW solar PV parkConnection contract
3.9 MW solar PV park · RoșioriPermit valid
3.9 MW solar PV park · ChișlazPermit expired
3.7 MW solar PV park · SălardPermit valid
3.5 MW solar PV parkConnection contract
3.0 MW solar PV parkConnection contract
3.0 MW solar PV park · PopeștiConnection contract
3.0 MW solar PV park · DrăgăneștiPermit valid
2.9 MW solar PV park · NojoridConnection contract
2.8 MW solar PV park · CiumeghiuConnection contract
2.7 MW solar PV park · OșorheiConnection contract
2.6 MW solar PV parkConnection contract
2.2 MW solar PV park · SântandreiPermit expired
2.2 MW solar PV park · SântandreiConnection contract
2.1 MW solar PV park · ChișlazConnection contract
2.0 MW solar PV parkPermit valid
1.9 MW solar PV park · SântandreiConnection contract
1.8 MW solar PV park · AbramConnection contract
1.7 MW solar PV park · CiumeghiuConnection contract
1.3 MW solar PV park · OradeaConnection contract
1.3 MW solar PV park · OradeaPermit valid
1.3 MW solar PV park · BorodConnection contract
1.1 MW solar PV park · Sânnicolau-RomânConnection contract
1.1 MW solar PV park · BratcaConnection contract
1.0 MW solar PV park · OradeaConnection contract