Energy projects in Hunedoara

In Hunedoara County, 33 projects above 1 MW are requesting grid connection, 744 MW in total. 27 have a signed connection contract.

There are 28 solar PV parks (416 MW), 2 battery storage facilities (204 MW) and 2 hydropower plants (70 MW). The largest is 122.6 MW, and 3 projects exceed 50 MW. 3 projects hold a valid grid permit, and 3 have an expired permit.

ProjectStage
122.6 MW battery storage facilityConnection contract
81.7 MW battery storage facilityConnection contract
Energy project 53.5 MW · CălanConnection contract
50.0 MW solar PV park · Râu AlbPermit expired
49.9 MW solar PV park · Râu AlbConnection contract
49.9 MW solar PV park · BăciaConnection contract
48.5 MW solar PV parkPermit expired
45.1 MW hydropower plant · Bretea RomânăConnection contract
43.2 MW solar PV parkConnection contract
41.1 MW solar PV park · Sântămăria de PiatrăConnection contract
38.1 MW solar PV park · Sântămăria de PiatrăConnection contract
31.2 MW solar PV park · GrohoțelePermit valid
24.5 MW hydropower plant · AninoasaConnection contract
6.7 MW solar PV parkPermit valid
5.1 MW solar PV parkConnection contract
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkConnection contract
5.0 MW solar PV parkConnection contract
4.5 MW solar PV parkConnection contract
4.2 MW solar PV parkConnection contract
3.6 MW solar PV park · RomosConnection contract
3.6 MW solar PV park · GeoagiuConnection contract
3.3 MW solar PV park · Bretea RomânăConnection contract
2.7 MW solar PV park · GeoagiuConnection contract
2.2 MW solar PV park · BăciaConnection contract
2.0 MW solar PV park · CălanConnection contract
2.0 MW solar PV parkConnection contract
2.0 MW solar PV parkPermit expired
1.9 MW solar PV park · HunedoaraConnection contract
1.8 MW solar PV parkConnection contract
1.4 MW solar PV park · HunedoaraConnection contract
1.3 MW solar PV park · Aurel VlaicuConnection contract
1.0 MW solar PV parkConnection contract

Other counties