Energy projects in Brașov

In Brașov County, 57 projects above 1 MW are requesting grid connection, 1,204 MW in total. 48 have a signed connection contract.

There are 53 solar PV parks (1,048 MW), 3 hydropower plants (7 MW) and 1 battery storage facility (149 MW). The largest is 250.0 MW, and 3 projects exceed 50 MW. 9 projects hold a valid grid permit.

ProjectStage
250.0 MW solar PV parkConnection contract
148.7 MW battery storage facilityConnection contract
70.3 MW solar PV park · PârâuPermit valid
49.8 MW solar PV park · CrizbavConnection contract
49.8 MW solar PV park · HărmanPermit valid
48.1 MW solar PV park · HomorodConnection contract
48.0 MW solar PV park · RupeaConnection contract
42.9 MW solar PV park · PrejmerConnection contract
42.0 MW solar PV park · BodPermit valid
40.2 MW solar PV park · RupeaConnection contract
40.1 MW solar PV park · MândraConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
30.8 MW solar PV park · BrașovConnection contract
21.0 MW solar PV park · ȘercaiaPermit valid
19.9 MW solar PV parkConnection contract
18.9 MW solar PV park · BrașovPermit valid
18.0 MW solar PV park · BrașovConnection contract
7.4 MW solar PV park · RâșnovConnection contract
7.0 MW solar PV park · PurcăreniConnection contract
6.4 MW solar PV parkConnection contract
5.0 MW solar PV park · ZărneștiConnection contract
5.0 MW solar PV park · ZărneștiConnection contract
5.0 MW solar PV parkConnection contract
4.9 MW solar PV park · MândraConnection contract
4.9 MW solar PV parkPermit valid
4.8 MW solar PV park · SăceleConnection contract
4.7 MW solar PV park · TărlungeniConnection contract
4.5 MW solar PV park · HălchiuConnection contract
4.5 MW solar PV park · ZărneștiConnection contract
4.5 MW solar PV park · ZărneștiConnection contract
3.9 MW solar PV park · BecleanPermit valid
3.9 MW solar PV park · BecleanConnection contract
3.8 MW solar PV park · Rupea GarăConnection contract
3.7 MW solar PV parkConnection contract
3.0 MW solar PV park · GhimbavPermit valid
3.0 MW solar PV parkConnection contract
2.9 MW solar PV parkConnection contract
2.6 MW hydropower plant · SebeșConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.4 MW hydropower plant · Viștea de JosConnection contract
2.2 MW solar PV parkConnection contract
2.1 MW solar PV park · HălchiuConnection contract
2.0 MW solar PV parkConnection contract
2.0 MW solar PV parkConnection contract
2.0 MW solar PV parkConnection contract
1.8 MW solar PV park · JibertConnection contract
1.7 MW solar PV parkConnection contract
1.6 MW solar PV parkPermit valid
1.6 MW hydropower plant · HârșeniConnection contract
1.5 MW solar PV parkConnection contract
1.2 MW solar PV park · BrașovConnection contract