Solar PV parks in Brașov

In Brașov County, 53 solar PV projects above 1 MW are requesting grid connection, 1,048 MW in total. 44 have a signed connection contract.

The largest is 250.0 MW, and 2 projects exceed 50 MW. 9 projects hold a valid grid permit.

ProjectStage
250.0 MW solar PV parkConnection contract
70.3 MW solar PV park · PârâuPermit valid
49.8 MW solar PV park · HărmanPermit valid
49.8 MW solar PV park · CrizbavConnection contract
48.1 MW solar PV park · HomorodConnection contract
48.0 MW solar PV park · RupeaConnection contract
42.9 MW solar PV park · PrejmerConnection contract
42.0 MW solar PV park · BodPermit valid
40.2 MW solar PV park · RupeaConnection contract
40.1 MW solar PV park · MândraConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
34.5 MW solar PV park · Ucea de SusConnection contract
30.8 MW solar PV park · BrașovConnection contract
21.0 MW solar PV park · ȘercaiaPermit valid
19.9 MW solar PV parkConnection contract
18.9 MW solar PV park · BrașovPermit valid
18.0 MW solar PV park · BrașovConnection contract
7.4 MW solar PV park · RâșnovConnection contract
7.0 MW solar PV park · PurcăreniConnection contract
6.4 MW solar PV parkConnection contract
5.0 MW solar PV park · ZărneștiConnection contract
5.0 MW solar PV parkConnection contract
5.0 MW solar PV park · ZărneștiConnection contract
4.9 MW solar PV parkPermit valid
4.9 MW solar PV park · MândraConnection contract
4.8 MW solar PV park · SăceleConnection contract
4.7 MW solar PV park · TărlungeniConnection contract
4.5 MW solar PV park · HălchiuConnection contract
4.5 MW solar PV park · ZărneștiConnection contract
4.5 MW solar PV park · ZărneștiConnection contract
3.9 MW solar PV park · BecleanPermit valid
3.9 MW solar PV park · BecleanConnection contract
3.8 MW solar PV park · Rupea GarăConnection contract
3.7 MW solar PV parkConnection contract
3.0 MW solar PV park · GhimbavPermit valid
3.0 MW solar PV parkConnection contract
2.9 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.2 MW solar PV parkConnection contract
2.1 MW solar PV park · HălchiuConnection contract
2.0 MW solar PV parkConnection contract
2.0 MW solar PV parkConnection contract
2.0 MW solar PV parkConnection contract
1.8 MW solar PV park · JibertConnection contract
1.7 MW solar PV parkConnection contract
1.6 MW solar PV parkPermit valid
1.5 MW solar PV parkConnection contract
1.2 MW solar PV park · BrașovConnection contract