In Gorj County, 73 projects above 1 MW are requesting grid connection, 2,343 MW in total. 45 have a signed connection contract.

There are 39 solar PV parks (928 MW), 16 hybrid projects (149 MW), 9 battery storage facilities (535 MW), 3 hydropower plants (44 MW) and 1 wind farm (50 MW). The largest is 482.5 MW, and 7 projects exceed 50 MW. 23 projects hold a valid grid permit, and 5 have an expired permit.

ProjectStage
482.5 MW energy projectConnection contract
393.8 MW battery storage facilityPermit valid
285.3 MW solar PV parkConnection contract
131.3 MW solar PV parkConnection contract
98.5 MW solar PV parkConnection contract
73.5 MW energy projectConnection contract
57.7 MW energy projectConnection contract
49.8 MW hybrid projectPermit valid
49.6 MW wind farm · PeștișaniPermit valid
49.5 MW solar PV park · BorăscuConnection contract
49.5 MW solar PV park · BolboșiConnection contract
48.8 MW battery storage facilityConnection contract
48.0 MW battery storage facility · StejariPermit valid
45.8 MW solar PV parkConnection contract
44.8 MW solar PV park · CiuperceniConnection contract
44.5 MW solar PV parkConnection contract
43.2 MW solar PV parkConnection contract
42.4 MW hybrid project · VladimirConnection contract
40.5 MW hydropower plant · Bumbești-JiuConnection contract
16.7 MW energy projectConnection contract
15.0 MW solar PV park · RovinariConnection contract
14.0 MW battery storage facility · Târgu CărbuneștiConnection contract
10.0 MW solar PV park · FărcășeștiConnection contract
9.8 MW hybrid project · Târgu CărbuneștiConnection contract
9.7 MW solar PV park · DăneștiConnection contract
9.3 MW hybrid project · Târgu CărbuneștiConnection contract
7.1 MW battery storage facility · RovinariConnection contract
7.1 MW battery storage facility · RovinariConnection contract
6.8 MW battery storage facility · StejariPermit valid
6.7 MW battery storage facility · FărcășeștiPermit valid
6.5 MW solar PV parkPermit valid
6.4 MW thermal power plantConnection contract
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
5.0 MW solar PV parkPermit valid
4.8 MW solar PV park · BorăscuPermit expired
4.8 MW solar PV park · BolboșiConnection contract
4.8 MW solar PV park · BâlteniConnection contract
4.8 MW solar PV park · BâlteniPermit expired
4.5 MW hybrid project · TeleștiPermit valid
4.3 MW hybrid project · TurbureaConnection contract
4.2 MW solar PV parkConnection contract
4.0 MW hybrid projectConnection contract
4.0 MW hybrid projectConnection contract
4.0 MW hybrid projectConnection contract
3.5 MW hybrid projectConnection contract
3.4 MW solar PV park · Târgu CărbuneștiConnection contract
3.2 MW solar PV park · Târgu JiuConnection contract
3.1 MW hybrid project · ArcaniConnection contract
3.1 MW battery storage facilityPermit valid
3.0 MW solar PV parkPermit valid
3.0 MW solar PV parkPermit valid
3.0 MW solar PV park · BâlteniConnection contract
2.8 MW solar PV park · TeleștiPermit expired
2.6 MW hybrid project · BâlteniConnection contract
2.5 MW solar PV park · TeleștiConnection contract
2.5 MW solar PV park · Târgu JiuConnection contract
2.4 MW hybrid project · PlopșoruPermit valid
2.4 MW solar PV parkPermit valid
2.2 MW hybrid projectConnection contract
1.9 MW solar PV parkPermit expired
1.7 MW hydropower plantConnection contract
1.7 MW hydropower plantConnection contract
1.6 MW solar PV parkPermit expired
1.5 MW hybrid project · Târgu JiuPermit valid
1.2 MW hybrid project · BâlteniPermit valid
1.0 MW solar PV park · Târgu CărbuneștiConnection contract
1.0 MW solar PV park · RovinariConnection contract