In Covasna County, 20 projects above 1 MW are requesting grid connection, 373 MW in total. 19 have a signed connection contract.
There are 19 solar PV parks (358 MW) and 1 biomass plant (15 MW). The largest is 100.0 MW, and 2 projects exceed 50 MW. 1 project holds a valid grid permit.
| Project | Stage |
|---|---|
| 100.0 MW solar PV park · Reci | Connection contract |
| 74.1 MW solar PV park | Permit valid |
| 49.8 MW solar PV park · Zăbala | Connection contract |
| 36.2 MW solar PV park · Valea Mare | Connection contract |
| 21.0 MW solar PV park · Boroșneu Mare | Connection contract |
| 20.2 MW solar PV park · Arcuș | Connection contract |
| 20.0 MW solar PV park · Zăbala | Connection contract |
| 15.0 MW biomass plant · Reci | Connection contract |
| 4.2 MW solar PV park | Connection contract |
| 4.2 MW solar PV park · Catalina | Connection contract |
| 4.0 MW solar PV park · Arcuș | Connection contract |
| 4.0 MW solar PV park · Micloșoara | Connection contract |
| 3.0 MW solar PV park · Ghidfalău | Connection contract |
| 3.0 MW solar PV park · Arcuș | Connection contract |
| 3.0 MW solar PV park | Connection contract |
| 3.0 MW solar PV park · Arcuș | Connection contract |
| 2.9 MW solar PV park · Chiuruș | Connection contract |
| 2.0 MW solar PV park · Reci | Connection contract |
| 2.0 MW solar PV park · Ghidfalău | Connection contract |
| 1.0 MW solar PV park · Întorsura Buzăului | Connection contract |
Other counties
- Alba38
- Arad90
- Argeș50
- Bacău24
- Bihor67
- Bistrița-Năsăud14
- Botoșani21
- Brașov57
- Brăila69
- Bucharest14
- Buzău37
- Caraș-Severin35
- Călărași56
- Cluj34
- Constanța112
- Dâmbovița55
- Dolj129
- Galați48
- Giurgiu43
- Gorj73
- Harghita13
- Hunedoara33
- Ialomița25
- Iași27
- Ilfov42
- Maramureș21
- Mehedinți31
- Mureș55
- Neamț20
- Olt79
- Prahova41
- Satu Mare26
- Sălaj20
- Sibiu48
- Suceava16
- Teleorman44
- Timiș107
- Tulcea71
- Vaslui25
- Vâlcea22
- Vrancea25