Solar PV parks in Dâmbovița

In Dâmbovița County, 49 solar PV projects above 1 MW are requesting grid connection, 1,975 MW in total. 38 have a signed connection contract.

The largest is 213.4 MW, and 10 projects exceed 50 MW. 11 projects hold a valid grid permit.

ProjectStage
213.4 MW solar PV parkConnection contract
177.3 MW solar PV park · NiculeștiConnection contract
170.0 MW solar PV parkConnection contract
150.0 MW solar PV parkConnection contract
117.7 MW solar PV parkConnection contract
Energy project 97.0 MW · ButimanuConnection contract
70.4 MW solar PV parkConnection contract
67.5 MW solar PV park · RăscăețiConnection contract
61.9 MW solar PV parkConnection contract
50.6 MW solar PV park · RăcariConnection contract
50.0 MW solar PV park · ConțeștiPermit valid
50.0 MW solar PV park · ConțeștiPermit valid
49.9 MW solar PV park · Costeștii din ValeConnection contract
49.9 MW solar PV park · ConțeștiConnection contract
49.0 MW solar PV parkConnection contract
48.3 MW solar PV parkConnection contract
46.4 MW solar PV park · ȘotângaConnection contract
41.2 MW solar PV park · Costeștii din ValeConnection contract
40.4 MW solar PV park · RăcariConnection contract
40.2 MW solar PV parkConnection contract
35.7 MW solar PV park · Costeștii din ValeConnection contract
32.8 MW solar PV parkPermit valid
32.8 MW solar PV parkPermit valid
30.1 MW solar PV parkPermit valid
29.2 MW solar PV parkPermit valid
26.2 MW solar PV parkPermit valid
25.2 MW solar PV parkConnection contract
16.0 MW solar PV parkConnection contract
14.0 MW solar PV parkConnection contract
12.8 MW solar PV park · MăneștiPermit valid
7.8 MW solar PV park · Valea MareConnection contract
6.9 MW solar PV park · CrevediaConnection contract
6.9 MW solar PV parkConnection contract
6.7 MW solar PV park · RăcariConnection contract
6.6 MW solar PV parkConnection contract
5.1 MW solar PV parkConnection contract
5.0 MW solar PV park · UlmiConnection contract
4.6 MW solar PV park · SălcioaraConnection contract
4.5 MW solar PV park · Corbii MariConnection contract
4.0 MW solar PV park · Valea MareConnection contract
3.6 MW solar PV parkConnection contract
3.0 MW solar PV park · TârgovișteConnection contract
2.8 MW solar PV park · UlieștiPermit valid
2.7 MW solar PV park · RăscăețiPermit valid
2.6 MW solar PV park · Corbii MariConnection contract
2.5 MW solar PV parkConnection contract
1.8 MW solar PV park · TârgovișteConnection contract
1.3 MW solar PV park · VăcăreștiPermit valid
1.0 MW solar PV park · DragomireștiConnection contract

Other counties