Hybrid projects in Dolj

In Dolj County, 38 hybrid projects above 1 MW are requesting grid connection, 1,233 MW in total. 27 have a signed connection contract.

The largest is 347.9 MW, and 5 projects exceed 50 MW. 8 projects hold a valid grid permit, and 3 have an expired permit.

ProjectStage
347.9 MW hybrid projectConnection contract
195.6 MW hybrid projectConnection contract
194.8 MW hybrid projectConnection contract
138.0 MW hybrid projectConnection contract
82.9 MW hybrid projectConnection contract
39.2 MW hybrid project · DobreștiConnection contract
38.1 MW hybrid project · DobreștiConnection contract
27.0 MW hybrid projectConnection contract
25.9 MW hybrid project · GoieștiConnection contract
10.1 MW hybrid project · SadovaConnection contract
10.0 MW hybrid projectConnection contract
9.7 MW hybrid projectConnection contract
7.8 MW hybrid project · SadovaPermit valid
7.6 MW hybrid projectPermit expired
7.5 MW hybrid project · Șimnicu de SusPermit expired
7.2 MW hybrid project · SadovaPermit valid
7.1 MW hybrid project · PleșoiPermit valid
6.3 MW hybrid project · CraiovaConnection contract
6.1 MW hybrid projectPermit valid
6.0 MW hybrid projectPermit valid
5.6 MW hybrid project · PerișorConnection contract
5.0 MW hybrid project · OstroveniConnection contract
4.8 MW hybrid projectConnection contract
4.8 MW hybrid projectConnection contract
4.8 MW hybrid projectConnection contract
4.5 MW hybrid project · SopotConnection contract
3.7 MW hybrid projectConnection contract
3.0 MW hybrid projectConnection contract
2.9 MW hybrid projectConnection contract
2.9 MW hybrid projectConnection contract
2.8 MW hybrid projectConnection contract
2.5 MW hybrid project · PleșoiPermit valid
2.4 MW hybrid projectConnection contract
2.3 MW hybrid project · Ciupercenii NoiPermit expired
2.1 MW hybrid project · Ciupercenii NoiConnection contract
1.9 MW hybrid projectPermit valid
1.0 MW hybrid projectConnection contract
1.0 MW hybrid projectPermit valid