Solar PV parks in Ialomița

In Ialomița County, 20 solar PV projects above 1 MW are requesting grid connection, 340 MW in total. 17 have a signed connection contract.

The largest is 89.8 MW, and 2 projects exceed 50 MW. 2 projects hold a valid grid permit, and 1 has an expired permit.

ProjectStage
89.8 MW solar PV parkConnection contract
50.0 MW solar PV parkConnection contract
49.9 MW solar PV parkConnection contract
45.2 MW solar PV parkConnection contract
21.9 MW solar PV parkConnection contract
19.4 MW solar PV parkConnection contract
16.4 MW solar PV parkConnection contract
7.0 MW solar PV parkConnection contract
7.0 MW solar PV parkConnection contract
4.6 MW solar PV parkConnection contract
4.6 MW solar PV parkConnection contract
4.5 MW solar PV parkConnection contract
3.6 MW solar PV parkConnection contract
3.0 MW solar PV parkPermit valid
2.6 MW solar PV parkConnection contract
2.5 MW solar PV parkConnection contract
2.5 MW solar PV parkPermit valid
1.9 MW solar PV parkPermit expired
1.7 MW solar PV parkConnection contract
1.6 MW solar PV parkConnection contract