Wind farms in Iași

In Iași County, 7 wind projects above 1 MW are requesting grid connection, 797 MW in total. 5 have a signed connection contract.

The largest is 273.7 MW, and 6 projects exceed 50 MW. 2 projects have an expired permit.

ProjectStage
273.7 MW wind farmConnection contract
129.5 MW wind farmConnection contract
127.9 MW wind farmConnection contract
111.8 MW wind farm · ScobințiConnection contract
60.0 MW wind farmPermit expired
54.4 MW wind farmPermit expired
40.0 MW wind farm · SticlăriaConnection contract