Wind farms in Iași
In Iași County, 7 wind projects above 1 MW are requesting grid connection, 797 MW in total. 5 have a signed connection contract.
The largest is 273.7 MW, and 6 projects exceed 50 MW. 2 projects have an expired permit.
| Project | Stage |
|---|---|
| 273.7 MW wind farm | Connection contract |
| 129.5 MW wind farm | Connection contract |
| 127.9 MW wind farm | Connection contract |
| 111.8 MW wind farm · Scobinți | Connection contract |
| 60.0 MW wind farm | Permit expired |
| 54.4 MW wind farm | Permit expired |
| 40.0 MW wind farm · Sticlăria | Connection contract |
Other counties
- Alba38
- Arad90
- Argeș50
- Bacău24
- Bihor67
- Bistrița-Năsăud14
- Botoșani21
- Brașov57
- Brăila69
- Bucharest14
- Buzău37
- Caraș-Severin35
- Călărași56
- Cluj34
- Constanța112
- Covasna20
- Dâmbovița55
- Dolj129
- Galați48
- Giurgiu43
- Gorj73
- Harghita13
- Hunedoara33
- Ialomița25
- Ilfov42
- Maramureș21
- Mehedinți31
- Mureș55
- Neamț20
- Olt79
- Prahova41
- Satu Mare26
- Sălaj20
- Sibiu48
- Suceava16
- Teleorman44
- Timiș107
- Tulcea71
- Vaslui25
- Vâlcea22
- Vrancea25