In Olt County, 37 hybrid projects above 1 MW are requesting grid connection, 807 MW in total. 21 have a signed connection contract.

The largest is 216.1 MW, and 4 projects exceed 50 MW. 13 projects hold a valid grid permit, and 3 have an expired permit.

ProjectStage
216.1 MW hybrid projectConnection contract
99.4 MW hybrid project · BrebeniConnection contract
99.4 MW hybrid project · BrebeniConnection contract
53.1 MW hybrid project · MărunțeiPermit valid
42.9 MW hybrid project · CorbuPermit valid
37.4 MW hybrid project · OporeluConnection contract
20.6 MW hybrid project · BobiceștiConnection contract
20.6 MW hybrid project · BobiceștiConnection contract
14.5 MW hybrid projectPermit expired
11.2 MW hybrid project · StudinaConnection contract
11.0 MW hybrid projectConnection contract
10.3 MW hybrid project · Valea MareConnection contract
10.3 MW hybrid project · Valea MareConnection contract
10.3 MW hybrid project · Valea MarePermit valid
10.3 MW hybrid project · Valea MareConnection contract
10.0 MW hybrid project · StudinaConnection contract
10.0 MW hybrid project · BobiceștiConnection contract
10.0 MW hybrid projectConnection contract
10.0 MW hybrid projectConnection contract
10.0 MW hybrid project · BobiceștiConnection contract
9.2 MW hybrid project · DobrosloveniPermit valid
9.2 MW hybrid project · DobrosloveniPermit valid
8.4 MW hybrid projectPermit valid
7.7 MW hybrid projectPermit valid
7.5 MW hybrid project · Osica de SusPermit expired
7.2 MW hybrid projectConnection contract
5.0 MW hybrid projectConnection contract
5.0 MW hybrid project · StoeneștiConnection contract
4.8 MW hybrid projectConnection contract
4.8 MW hybrid projectPermit valid
4.8 MW hybrid project · BobiceștiPermit valid
4.8 MW hybrid projectPermit valid
4.8 MW hybrid project · CurtișoaraConnection contract
2.8 MW hybrid projectPermit expired
2.0 MW hybrid projectPermit valid
1.2 MW hybrid project · LeleascaPermit valid
1.0 MW hybrid projectPermit valid