Hybrid projects in Timiș
In Timiș County, 8 hybrid projects above 1 MW are requesting grid connection, 582 MW in total. 1 has a signed connection contract.
The largest is 244.4 MW, and 2 projects exceed 50 MW. 7 projects hold a valid grid permit.
| Project | Stage |
|---|---|
| 244.4 MW hybrid project | Connection contract |
| 86.0 MW hybrid project | Permit valid |
| 41.9 MW hybrid project | Permit valid |
| 41.9 MW hybrid project | Permit valid |
| 41.9 MW hybrid project | Permit valid |
| 41.9 MW hybrid project | Permit valid |
| 41.9 MW hybrid project | Permit valid |
| 41.9 MW hybrid project | Permit valid |
Other counties
- Alba38
- Arad90
- Argeș50
- Bacău24
- Bihor67
- Bistrița-Năsăud14
- Botoșani21
- Brașov57
- Brăila69
- Bucharest14
- Buzău37
- Caraș-Severin35
- Călărași56
- Cluj34
- Constanța112
- Covasna20
- Dâmbovița55
- Dolj129
- Galați48
- Giurgiu43
- Gorj73
- Harghita13
- Hunedoara33
- Ialomița25
- Iași27
- Ilfov42
- Maramureș21
- Mehedinți31
- Mureș55
- Neamț20
- Olt79
- Prahova41
- Satu Mare26
- Sălaj20
- Sibiu48
- Suceava16
- Teleorman44
- Tulcea71
- Vaslui25
- Vâlcea22
- Vrancea25