Solar PV parks in Tulcea
In Tulcea County, 26 solar PV projects above 1 MW are requesting grid connection, 198 MW in total. 17 have a signed connection contract.
The largest is 50.7 MW. 6 projects hold a valid grid permit, and 3 have an expired permit.
| Project | Stage |
|---|---|
| 50.7 MW solar PV park | Permit valid |
| 39.9 MW solar PV park | Connection contract |
| 23.8 MW solar PV park | Connection contract |
| 7.8 MW solar PV park | Permit expired |
| 6.9 MW solar PV park | Permit valid |
| 6.3 MW solar PV park | Connection contract |
| 5.1 MW solar PV park | Connection contract |
| 4.9 MW solar PV park | Connection contract |
| 4.5 MW solar PV park | Connection contract |
| 4.5 MW solar PV park | Permit valid |
| 4.5 MW solar PV park | Connection contract |
| 4.5 MW solar PV park | Permit valid |
| 4.2 MW solar PV park | Connection contract |
| 3.0 MW solar PV park | Connection contract |
| 3.0 MW solar PV park | Permit valid |
| 2.9 MW solar PV park | Connection contract |
| 2.9 MW solar PV park | Permit valid |
| 2.6 MW solar PV park | Connection contract |
| 2.6 MW solar PV park | Connection contract |
| 2.4 MW solar PV park | Connection contract |
| 2.3 MW solar PV park | Connection contract |
| 2.1 MW solar PV park | Permit expired |
| 2.0 MW solar PV park | Connection contract |
| 2.0 MW solar PV park | Permit expired |
| 1.5 MW solar PV park | Connection contract |
| 1.0 MW solar PV park | Connection contract |
Other counties
- Alba38
- Arad90
- Argeș50
- Bacău24
- Bihor67
- Bistrița-Năsăud14
- Botoșani21
- Brașov57
- Brăila69
- Bucharest14
- Buzău37
- Caraș-Severin35
- Călărași56
- Cluj34
- Constanța112
- Covasna20
- Dâmbovița55
- Dolj129
- Galați48
- Giurgiu43
- Gorj73
- Harghita13
- Hunedoara33
- Ialomița25
- Iași27
- Ilfov42
- Maramureș21
- Mehedinți31
- Mureș55
- Neamț20
- Olt79
- Prahova41
- Satu Mare26
- Sălaj20
- Sibiu48
- Suceava16
- Teleorman44
- Timiș107
- Vaslui25
- Vâlcea22
- Vrancea25