Battery storage facilities in Constanța

In Constanța County, 22 battery storage projects above 1 MW are requesting grid connection, 2,497 MW in total. 4 have a signed connection contract.

The largest is 503.8 MW, and 10 projects exceed 50 MW. 12 projects hold a valid grid permit, and 6 have an expired permit.