Solar PV parks in Constanța

In Constanța County, 37 solar PV projects above 1 MW are requesting grid connection, 878 MW in total. 21 have a signed connection contract.

The largest is 198.4 MW, and 4 projects exceed 50 MW. 11 projects hold a valid grid permit, and 5 have an expired permit.

ProjectStage
198.4 MW solar PV parkPermit valid
100.0 MW solar PV parkPermit valid
78.6 MW solar PV park · DeleniConnection contract
52.0 MW solar PV park · DeleniConnection contract
48.8 MW solar PV parkConnection contract
48.3 MW solar PV parkPermit expired
Energy project 46.8 MW · OvidiuConnection contract
46.2 MW solar PV parkConnection contract
46.2 MW solar PV parkPermit valid
30.0 MW solar PV parkPermit valid
28.1 MW solar PV parkConnection contract
27.7 MW solar PV parkConnection contract
24.0 MW solar PV parkPermit valid
22.1 MW solar PV parkConnection contract
12.3 MW solar PV parkPermit valid
4.9 MW solar PV parkPermit valid
4.7 MW solar PV parkConnection contract
4.5 MW solar PV parkConnection contract
4.5 MW solar PV parkConnection contract
4.4 MW solar PV parkPermit valid
4.2 MW solar PV parkConnection contract
4.2 MW solar PV parkConnection contract
4.2 MW solar PV parkPermit valid
4.0 MW solar PV parkConnection contract
3.6 MW solar PV parkPermit expired
3.5 MW solar PV parkConnection contract
3.0 MW solar PV parkConnection contract
2.8 MW solar PV parkConnection contract
2.7 MW solar PV parkConnection contract
2.3 MW solar PV parkPermit expired
2.2 MW solar PV parkPermit valid
2.1 MW solar PV parkConnection contract
1.6 MW solar PV parkPermit valid
1.5 MW solar PV parkPermit expired
1.4 MW solar PV parkPermit expired
1.1 MW solar PV parkConnection contract
1.1 MW solar PV parkConnection contract